Activity On Arrow Diagram(AOA)

Activity Precedence Table

Activity

Immediate Predecessor

Duration(weeks)

A

2

B

3

C

A,B

11

D

C

3

E

D

2

F

E

1

AOA new

Key Details :

A = Proposal and preparation

B = Project planning, design and estimation

C = Web development

D = Testing, Debugging and wrap up project

E = Project Documentation

F = Presentation

 

Prepared By Yeoh Tze Wei (Team Leader)

Checked By Goh Seng Yiung (Documentation Manager)

Posted By Phang Xiao Shen (Design Manager)