Activity Precedence Table
Activity | Immediate Predecessor | Duration(weeks) |
A | − | 2 |
B | − | 3 |
C | A,B | 11 |
D | C | 3 |
E | D | 2 |
F | E | 1 |
Key Details :
A = Proposal and preparation
B = Project planning, design and estimation
C = Web development
D = Testing, Debugging and wrap up project
E = Project Documentation
F = Presentation
Prepared By Yeoh Tze Wei (Team Leader)
Checked By Goh Seng Yiung (Documentation Manager)
Posted By Phang Xiao Shen (Design Manager)
1 comments on "Activity On Arrow Diagram(AOA)"