Activity On Arrow Diagram(AOA)


Activity Precedence Table

Activity

Immediate Predecessor

Duration(weeks)

A

2

B

3

C

A,B

11

D

C

3

E

D

2

F

E

1

AOA new

Key Details :

A = Proposal and preparation

B = Project planning, design and estimation

C = Web development

D = Testing, Debugging and wrap up project

E = Project Documentation

F = Presentation

 

Prepared By Yeoh Tze Wei (Team Leader)

Checked By Goh Seng Yiung (Documentation Manager)

Posted By Phang Xiao Shen (Design Manager)

1 comments on "Activity On Arrow Diagram(AOA)"

langdack on March 5, 2022 at 1:00 AM said...

everquest titanium - www.titanium-arts.com
In 2021, Tipeye used ford fusion titanium Inc. was men\'s titanium wedding bands acquired by titanium cost a consortium of U.S. and International Trade and Gaming Authority (USGA) for approximately $3.1 토토 사이트 billion best titanium flat iron in

Post a Comment

 

web prepared by

Phang Xiao Shen
Design Manager

Contact

ezzshop2009@gmail.com

eEasy Shopping Store Copyright 2008 Shoppaholic Designed by Ipiet Templates Image by Tadpole's Notez Distributed by Blogger Blog Templates