Tasks Start Date Duration (days) End Date
Proposal and preparation 06/18/2009 10 6/28/2009
Project planning, design and estimation 06/29/2009 20 7/19/2009
Web development 06/22/2009 83 9/13/2009
Testing, debugging and wrap up 08/24/2009 20 9/13/2009
Documentation 08/31/2009 13 9/13/2009
Presentation 09/14/2009 4 9/18/2009